|
|
The front entrances of Thorndale station, looking northwest on September 29, 2012, the first full day the station was open after renovation. The pilasters framing the doors and the ornamentation around the light fixtures convey the station's Prairie School influences. For a larger view, click here. (Photo by Graham Garfield) |
Thorndale
(5900N/1200W)
Thorndale Avenue and
Broadway, Edgewater
Service Notes:
Red Line: Howard
Owl Service
Quick Facts:
Address: 1118 W. Thorndale Avenue
Established: February 14, 1915
Original Line: Northwestern Elevated Railroad
Previous Names: none
Rebuilt: 1921, 2012
Skip-Stop Type:
Station
Status: In Use
History:
"L" service first entered north Chicago and Evanston by way of an agreement to use the tracks of the Chicago, Milwaukee and St. Paul Railway's tracks, replacing the steam service that the St. Paul had previously provided. The Chicago City Council authorized the electrification of the tracks of the Chicago, Milwaukee and St. Paul Railroad's tracks from Graceland Avenue (Irving Park Road) to the city limits on July 1, 1907. Unlike Evanston (as per the 1907 franchise agreement from the city), the Chicago City Council did not require that the grade-level tracks be elevated, but they did prohibit the use of a third rail for safety's sake, necessitating the use of overhead trolley wire. "L" service north of Wilson to Central Avenue in Evanston began on May 16, 1908.
Track Elevation and a New Station
In the mid-1910s, the Northwestern Elevated began to elevate the tracks north from Wilson to Howard, but work was slow due to the city's refusal to close intersecting streets and the narrow right-of-way. The elevation work involved complex staging and the temporary relocation of tracks to maintain service while building the new elevated embankment in the same right-of-way.
A view looking north during the track elevation project circa 1915 shows the first, temporary Thorndale station platforms. For a larger view, click here. (Photo by A.F. Scholz Photography, from M.D. McCarter Collection) |
Unlike the other locations along the new "L" extension where there are currently stations, the St. Paul had not had a station at Thorndale Avenue. The station was added as a result of community advocacy and pressure. Following the extension of "L" service through the Edgewater community, development accelerated along both Winthrop and Kenmore to the east of the tracks, and west of Broadway on the west side of the tracks, with scores of apartment buildings increasing population density. New residents of this central area of Edgewater wanted a shorter walk to the “L”, so they petitioned for a new station to be added between the two existing stations at North Edgewater (Granville) and Edgewater (Bryn Mawr). Petitioning began as early as August 1913 -- an August 30 article in the Chicago Tribune notes that the Thorndale Improvement Association had enlisted women voters in a petition drive to secure a station at Thorndale, and that in short order they had secured more than 1,200 signatures. The Illinois Public Utilities Commission issued an order on November 12, 1914 to the Northwestern Elevated Railroad to add a station stop at Thorndale.1
Not everyone was onboard with adding a station at Thorndale, however -- not only did the Northwestern Elevated not voluntarily agree, but some local residents and institutions resisted as well. An item in the December 23, 1914 issue of the Chicago Tribune indicated that A.T.H. Brower, of 1010 W. Bryn Mawr and past president of the Edgewater Improvement Association along with Edgewater Architect J.E.O. Pridmore, president of the North Edgewater Improvement Association, Mrs. Ella Flagg Young, Superintendent of the Chicago Board of Education, and Harriet A. Eckhart, principal of the George B. Swift school, asked the Illinois Public Utilities Commission to modify its order. The Chicago Board of Education felt that if a station were added at Thorndale, it would make the street a "heavily traveled thoroughfare and would interfere with the work of the Swift School." Supporters of the Thorndale station threatened to appeal to the Superior Court of Sangamon County. It is not clear how the controversy was resolved, but supporters of a station at Thorndale won -- the station was opened less than two months later.2
Thorndale station is seen looking west on Thorndale Avenue circa the 1940s. Although the details have changed -- the partitions, furniture, and stairway enclosures on the platform; the identification sign on the viaduct; the cars and street lights on the street -- the structure is the same today. For a larger view, click here. (Photo from the CTA Collection) |
Thorndale opened on February 14, 1915, amid the project to elevate the North Side "L" tracks; Edgewater Beach [Berwyn] station was also added during the elevation project. This meant that the first Thorndale station was actually a temporary facility; based on the only photo of it known to exist, it was a simple, wooden structure. In early 1916, trains were moved onto a temporary trestle, allowing demolition of the original tracks and stations, but construction of a permanent embankment had to wait until the end of World War I due to a materials shortage. This seems to indicate that the Thorndale station at this time was temporary, as the embankment had not been completed.
As part of the track elevation, a new, permanent station was constructed. The entrance to the "L" station was located on the north side of Thorndale Avenue. The station had a design typical of the facilities built as part of the Wilson-Howard elevation project. Designed by architect Charles P. Rawson and engineered by C.F Loweth, the architectural design was a Prairie School-influenced vernacular form, with the Prairie influence seen most acutely in the ornamental cement pilasters on the front facade and in the details of the wooden doors, windows, and ticket agents' booths. The exterior was brick and cast concrete with a bedford stone base, wooden doors and large plate glass windows and transoms. Ornamental globed light fixtures decorated the pilaster capitals. The station house was centered within the solid-fill embankment, with retail spaces flanking it on both sides filling in the remaining width of the embankment.
The interior of Thorndale station is largely unchanged in this view looking north in 1971 -- the original glazed brick and plaster walls, flooring, and wooden ticket agent's booth are still original -- but the details have begun to change with the times, such as the fluorescent fixtures and the agent's booth painted white, to present a brighter, more "modern" appearance. For a larger view, click here. (CTA photo, from the Graham Garfield Collection) |
The interior was rendered in plaster, wood, glazed brick, and brick with terrazzo floors. There were arches stretching across the interior between the support columns. In the center of the interior, passengers found a decorative wooden ticket agent's booth with ornamental woodwork and a metal grille over the ticket agent's window. The station also had public restrooms.
There were four tracks through Thorndale station, but the outer two tracks were for express trains and were not served by the station. A single island platform between the two center tracks served local trains. The platform had wood decking and a canopy with metal columns down the center line which split into gently-curving gull wing-shaped roof supports, supporting a wooden canopy roof. The stairs were sheltered by wooden enclosures with wooden bottoms and windows on top, divided into rows of square panes, with swinging doors at the front of each enclosure. Like most of the stations north of Lawrence, there was originally an auxiliary exit, located on the south side of the street, descending down in the middle of retail spaces built under the elevated. The auxiliary exit was closed and removed some time in the CTA era.
In December 1920, it was reported that the Thorndale station, along with Argyle, Edgewater Beach, Bryn Mawr, Granville, and Jarvis, would be completed by late Spring 1921.3 By early 1922, the new four track mainline was completed, allowing full express service to the city limits.
Due to low ridership and a budget crunch requiring economization, on February 9, 1992, Thorndale became a "part-time" station, closed Sundays and holidays to save the cost of the station ticket agent. The station's part-time status was repealed on July 9, 1995, after which the station would remained open seven days a week.
Recent Developments
The island platform at Thorndale, looking south on September 4, 2001, from just north of the north stairs to the station house. The canopy supports and roof structure all date from the construction of the station in the early 1920s. The new gray Green Line Graphic Standard sign was added in the late 1990s, though in a modified fashion: the colored tabs on either side (which would be red here) are omitted because the existing brackets could not accommodate them. For a larger view, click here. (Photo by Graham Garfield) |
Thorndale was one of five Chicago Transit Authority sites that were the first to provide access to vehicles belonging to I-GO, a car-sharing program. At their August 11, 2004 meeting, the Chicago Transit Board approved the agreement between the CTA , the Center for Neighborhood Technology (CNT) and its affiliate I-GO Car Sharing (I-GO) to promote the use of public transportation by providing additional options for public transit users. The agreement established a yearlong pilot program where members can access I-GO vehicles at locations adjacent to or near public transportation.
In 2006, the station name signs and column signs on the platform were replaced, with Green Line Graphic Standard signs replacing the KDR Standard graphics, and new entrance signs installed as part of a signage upgrade project on the Red Line. As part of this effort, the station also received granite compass roses inset into the sidewalk in front of the station entrance to assist customers leaving the station to navigate their way, and three-sided galvanized steel pylons in the station house and on the platform to display maps and station timetables.
In 2008, the canopy at Thorndale was refurbished. The roof was removed and replaced with a new corrugated metal top. Wood paneling was installed under the metal cover, visible to passengers standing on the platform and looking up at the canopy, to maintain the historic aesthetic and design of the station canopy. The metal canopy supports were stripped and repainted. New lighting was also installed as part of the renovation. Around the same time, a white, perforated drop ceiling and new lighting were installed inside the station as well.
North Red Line Life-Extension Renovations
By the early 21st century, the stations, track, and elevated infrastructure on the north Red Line, between Wilson and Howard, were in severe need of rehabilitation, both to maintain a good state of repair as well as to modernize certain systems and amenities. The scale of the work and the funding necessary to undertake it were large enough that a broad study and planning effort were needed to properly scope the work and apply for sufficient funding. While this study was undertaken, and due to the presumed amount of time it would take to complete the study, secure funding, and complete design engineering, the CTA felt it was necessary to undertake modest-scale renovations in the meantime to extend the life of the existing infrastructure.
Construction crews work to remove the old wooden decking and joists on the Thorndale platform on August 18, 2012, the day after the station closed. The work will leave only the steel canopy structure and support stringers, which were refurbished, reinforced, and reused in the new station. After additional supports were installed, a new precast concrete deck was erected. For a larger view, click here. (CTA Photo) |
On February 8, 2012, the Chicago Transit Board approved the awarding of a design/build contract to Kiewit Infrastructure Co. to rehabilitate seven rail stations on the North Main Line section of the Red Line: Jarvis, Morse, Granville, Thorndale, Berwyn, Argyle and Lawrence. The work would provide a life-extension for the seven stations until a long-term capital improvement plan is determined for this portion of the Red Line as part of the Red-Purple Modernization Project (see below). "These interim improvements are important because we cannot postpone repairs which need our immediate attention. The CTA wants to be good stewards of the infrastructure we have now, as we continue to plan for the future and pursue additional funding," said CTA President Forrest Claypool. "This contract will allow us to quickly address some much needed capital maintenance work, while also improving the quality and experience for our riders and neighbors."
Kiewit Infrastructure Co. was awarded the contract to through a competitive bid process. Design work began in Spring 2012. Per the terms of the contract, construction was to conclude in early 2013 (though most work was actually completed by the end of 2012) and was not to exceed $57.4 million for services, labor and materials.
Construction plans included temporary station closures for no more than six weeks. Adjacent stations were not closed simultaneously. To minimize impact to customers, service reroutes were scheduled for overnight and weekends only.
Improvement work at each location included renovations to the station facilities, the viaduct, and the tracks. The station houses received new windows, doors and exterior lighting; exterior tuck pointing; improved station layouts; new turnstiles; new interior finishes, including new wall tiling, floors, walls and ceilings; new signage and interior lighting; and site improvements including sidewalk repairs and new bike racks. The platform deck structure and foundation was replaced, the platform fixtures, furnishings and canopy improved, and a new customer communication system installed. Concrete repairs to the viaducts and to the track-level walls were made at each station, and a new waterproofing and drainage system was installed. In addition, the viaducts received painting/coating and new, brighter lighting under the viaducts. New track, ties, and ballast was laid through the station area.4
The interior of the renovated Thorndale station is seen looking west in the unpaid area on September 29, 2012. The rehabilitation gutted the interior and installed new terrazzo flooring, wall tiles, cement plaster walls and ceiling, lighting, and fixtures. The floor space was also expanded into adjacent former retail space -- the farecard vending machines are in what was formerly a separate storefront. For a larger view, click here. (Photo by Graham Garfield) |
The exterior masonry, including the brick walls and concrete trim, was cleaned and the brickwork re-tuckpointed. The wooden door and window frames were removed and a new dark brown aluminum storefront installed. New globed lights were installed on the piers.
Inside, the station house was gutted down to the structural shell. The retail spaces that originally flanked the station house on both sides were demolished and the common walls removed so that the station interior could be expanded into the former rental spaces. The concession stand added inside the station house opposite the agent's booth at an earlier date was removed as well. The enlarged station interior allowed for a more open space and improved passenger circulation. Farecard vending machines and the new Customer Assistant kiosk were installed in the former west retail space. The floor space formerly occupied by the east rental space was divided up, with the area toward the front of the station included in the newly expanded passenger space. A new wall was constructed roughly where the former wall between the station and rental space was to create a new enclosure, with the space in the middle of the station house for a concessionaire and the space in the rear for storage.
The interior walls were clad in new white modular glazed brick similar to the original material, though with some difference -- while the walls were originally clad only to a height just over 6 feet from the floor with plaster walls and ornamental trim above, nearly all of the renovated station interior's walls were clad in glazed brick up to the new suspended plaster ceiling. In addition, the free-standing columns, which originally were also tiled up to a height of about 6 feet and topped with a bullnose trim course, had their tiling removed and were refinished with a smooth plaster-cement skim coat. The middle portions of the center set of arches were removed, with the curved arches modified to taper up to the ceiling; the arches on the ends of the colonnades remain intact. The original ornamental trim on the plaster walls was not replicated in the renovated station, except on the rear angled wall under the south stairs to the platform which retained the original design of glazed brick extended up to a height of 6 feet, topped with a rounded bullnose trim, and cement plaster coating the walls above. In addition, the decorative tan art marble piers with ornamental Prairie School capitals that flank the front doors inside the station were retained and refurbished, and the original cast iron newel posts at the bottom of the stair railings were kept. A new light gray terrazzo floor with dark gray edges along the walls was installed on top of a sand cushion, and a new plaster ceiling installed with recessed lighting. A new Customer Assistant kiosk was also installed, typical of those installed by the CTA at new Brown Line stations and other recent projects like the renovations at North/Clybourn and Cermak-Chinatown, with stainless steel lower walls and roof and glass panels on all side for maximum visibility.
The only portion of the renovated interior that maintained the original style of white tiled walls up to a six-foot height, topped with a bullnose trim, and ornamental trim in the cement-plaster walls above, were the walls on the sides and back of the south stairs up to the platform. The west side wall is seen looking south toward the turnstiles and front of the station on September 29, 2012. For a larger view, click here. (Photo by Graham Garfield) |
The wooden platform deck was completely removed and new foundations and supports installed to supplement the original structure. A new precast concrete deck was installed, edged with blue tactile panels. The original 1921 platform canopy was retained, stripped, rehabilitated, and repainted. The canopy roof installed in 2008, including the wooden paneling on the passenger-facing underside to replicate the look of the original roofing, was retained. New fixtures including galvanized steel windbreaks and stairway enclosures, new benches, lighting, sandboxes, speakers, and signage were installed.
Installing elevators to make all the stations wheelchair-accessible is not part of the short-term project.5 Work was also planned for the roofs of adjacent station buildings, so that inside concession spaces can be leased and begin to generate revenue for the Authority.6
Thorndale temporarily closed for renovation at the end of the day August 17, 2012. The station reopened following renovation at 10pm, Friday, September 28, 2012.
Funding for the station rehabilitation project is from the Federal Transportation Administration (FTA) and is part of the $1 billion Red Line investment project. The $1 billion capital investment is a combination of state, local and federal funds, which will support other Red Line projects including track and station renewal along the Dan Ryan branch; the renovation of the Clark/Division and Wilson stations; and several other track, substation and station renewal projects along the North Side Main Line.
In addition to the renovation of the station, a "bike hub" was built across from the station on the south side of Thorndale Avenue underneath the elevated structure, in the space formerly occupied by retail spaces and the auxiliary exit from the platform (long since removed). The Thorndale Bike Hub, which was developed in cooperation between Alderman Harry Osterman, CTA, and the Chicago Department of Transportation (CDOT), includes well-designed racks for a capacity of 60 bikes and a new bike fix-it station for cyclists to utilize. CDOT will install a safe crosswalk under the viaduct and there will be new, bright lighting throughout the space. The bike hub is planned to be completed a few months after the station reopened.7 Although independent of the station renovation project, the installation of the bike facility was timed to coincide with the station improvement work.
The scope for the seven north Red Line stations also included new original artwork. At Thorndale, the installation was a glass mosaic, entitled "Thrive," designed by Jim Bachor. The mosaic is located on the columns that forms the arched colonnade that crosses the width of the interior unpaid area. The design depicts plants growing from the base of the columns and blooming into different icons that represent the neighborhood, such as a painter's palette, a sand pail and a school building. The artwork was fabricated in Munich, Germany, and installed inside the station in October 2014.8
Red-Purple Lines Modernization (RPM) Project
Due to the deteriorating condition of the infrastructure on the Red Line north of Belmont and on the Purple Line, the CTA initiated the Red-Purple Modernization Project (RPM) to bring the existing transit stations, track systems, and structures into a state of good repair. The project, which stretches along the existing Red and Purple lines from north of Belmont station to Linden terminal, would help bring the existing transit line into a state of good repair, reduce travel times, improve access to job markets and destinations, and provide improved access to people with disabilities.
The project began in 2009 with a vision study to assess the scope of needs and develop a set of alternatives for study. In 2010, in accordance with the National Environmental Policy Act (NEPA), CTA and Federal Transit Administration (FTA) initiated the environmental review process for the project and undertook work to develop an Environmental Impact Statement (EIS). The process included numerous public meetings and input opportunities, and study of various alternatives for achieving a good state of repair for the infrastructure in the project area.
A number of alternatives are under consideration for the RPM project, including the comprehensive reconstruction of track, stations, and structures along the line. The four options currently under consideration and study, not including an FTA-required "no action" baseline scenario, include:
The Modernization with Station Consolidation option includes the consolidation of Thorndale station with the Granville and Bryn Mawr stations by closing the existing Thorndale station and adding entrances to Granville and Bryn Mawr -- at Glenlake Avenue for Granville station, approximately one block north of Thorndale station and one block south of Granville station.; and at Hollywood Avenue, approximately two blocks south of Thorndale station and one block north of Bryn Mawr station.
Other alternatives considered earlier in the study but subsequently eliminated due to public comment and further study included basic rehabilitation without adding a transfer station at Loyola, a modernization option with only three tracks between Lawrence and Howard, and a modernization option with a 2-track subway under Broadway.
The full-scale modernization envisioned on the Red-Purple Modernization Project could cost anywhere from $2.5 to $5 billion. On February 8, 2012, the CTA board retained Goldman Sachs & Co. to lead the search for public-private partnerships to help finance the reconstruction, which has no firm date. Goldman Sachs will work with Chicago-based Loop Capital Markets LLC and Estrada Hinojosa & Co., but will accept no fee for the first year as it determines the ability to raise private capital.
See CTA's Red & Purple Modernization page for more information about the scoping and planning process, and the various alternatives being considered.
The Thorndale island platform, looking north on September 29, 2012, following renovation. The gullwing canopy is original to the 1921 station, but the recent rehabilitation replaced the wood platform deck with precast concrete, refurbished the canopy structure, and provided new platform signage and furniture. The wood beadboard under the canopy, installed in 2008 to provide a similar appearance to the canopy's original roofing, was retained in the renovation. For a larger view, click here. (Photo by Graham Garfield) |
|
thorndale03.jpg (94k) |
thorndale-P-8_KDRsignNB-tempAB.jpg (403k) |
|
thorndale04.jpg (113k) |
|
thorndale05.jpg (89k) |
|
thorndale06.jpg (109k) |
|
thorndale07.jpg (246k) |
|
thorndale09.jpg (247k) |
|
thorndale10.jpg (231k) |
|
thorndale11.jpg (263k) |
|
thorndale12.jpg (227k) |
|
thorndale13.jpg (213k) |
|
thorndale15.jpg (228k) |
|
thorndale16.jpg (224k) |
|
thorndale19.jpg (180k) |
|
thorndale20.jpg (180k) |
|
thorndale22.jpg (203k) |
|
thorndale23.jpg (247k) |
|
thorndale25.jpg (275k) |
|
cta7004_20210728.jpg (353k) |
1. Blommaert, LeRoy. "Edgewater's "L" stations", Edgewater Historical Society, Vol. XXVI No. 1, Spring 2015. Accessed 19 November 2017.
2. Ibid.
3. "3 NEW STATIONS ON NORTH SIDE "L" READY JAN. 1." Chicago Daily Tribune, 1920 Dec. 1, pg. 21.
4. Red North Station Interim Improvements webpage. Chicago Transit Authority, retrieved 25 March 2012.
5. Hilkevitch, Jon. "$57.4 million facelift program OK'd for 7 North Side stops on CTA's Red Line." Chicago Tribune. 8 February 2012.
6. Roberts, Bob. "Major Renovations Coming To Multiple Red Line Stations." CBS Chicago. 9 February 2012.
7. "New Thorndale Station and Bike Hub." News from the 48th Ward: Focus on Thorndale. 48thward.org. Accessed 11 October 2012.
8. Woodard, Benjamin. "Artist Jim Bachor's Mosaic 'Thrive' Installed at Thorndale 'L' Station", DNAinfo Chicago, October 9, 2014.